Øresund Bridge road traffic restricted for eight weeks

A close view of an expansion joint spanning the Øresund Bridge roadway.
An expansion joint spans the Øresund Bridge deck. The operator says two large joints will be replaced from 31 August; this archive image does not show the work under way. Image: Øresundsbron / Editorial use

Road traffic across the Øresund Bridge will be restricted for about eight weeks from 31 August while two of the crossing’s largest expansion joints are replaced.

Listen to this articleNarrated - 9:12

The bridge operator says one lane will remain open in each direction along roughly 1.5 kilometres, with lower speed limits through the work zone. Preparatory barriers will affect traffic from 29 August, and the project is due to run until the end of October.

Vehicles wider than 3.75 metres and transports heavier than 100 tonnes cannot use the crossing during the work. Rail services are not affected.

The joints allow the bridge to move with temperature and load changes. Replacing two at once is intended to shorten the full maintenance programme by a year. Drivers are advised to avoid the busiest periods where possible and allow extra travel time.

#OresundBridge#RoadTraffic#CrossBorderTravel#Transport#SwedenNews#News